1. Basic level inspection: Check if the basic level is flat and solid. If there are any foreign objects, handle them properly.

2. Trial Shop: Determine the size of the geotextile according to site conditions and try to place it after cutting. The cut size must be correct.

3. Check that the width of the saree is proper, the overlap should be flat and the stiffness should be moderate.

4. Positioning: Use a hot air gun to bond the overlapping parts of the two geotextiles, and the spacing of the bonding points should be proper.

5. When sewing overlapping parts, the sutures should be straight and the stitches should be even.

St. After sewing, check whether the geotextile is laid flat and whether there are defects.

Requirements. If something happens that does not meet the requirements, it should be repaired in time.